Walter F. George Dam Long Term Riprap Repair

Share This:

A joint venture project with Continental Heavy Civil Corp & SJ Hamill Construction. Construction consisted of repairing 12,128 ft of the upstream face on two non-overflow earthen dikes along the Chattahoochee River in AL & GA. Existing armor stone & filter fabric was removed & replaced with 79,500 CY of new bedding stone, armor stone, & rip rap in three (3) phases that raised the dikes from EL 186’ to EL 205’ with 10,330 TN of asphalt paving along the top of the dike.